Relocation Timetable
This is a sample timeline to help you plan out your relocation and when to contact appropriate contractors and vendors. Often, you may not have six months to plan. Many vendors can work with tighter deadlines, but creating your own timeline should help you avoid unpleasant surprises. This is just a small sample of what's included in the complete Industrial Relocation Guide. Request your free copy.
| Weeks before Relocation | Activity
(start times) | |
|---|---|---|
| 24 |
Begin working with architect |
|
| 20 | Contractors apply for permits |
|
| 16 | Begin build-out & building modifications |
|
| 12 | Evaluate Telecom needs/changes |
|
| 10 | Create detailed moving plan |
|
| 6 | Plan
for new signs |
|
| 4 | Install
data cabling, furniture & office equipment Prepare plant electrical |
|
| 3 | Order printing |
|
| 2 | Asset
inventory Labeling & boxing |
|
| 1 | Begin movement of production equipment |
This is just a small sample of what's included in the complete Industrial Relocation Guide. Request your free copy.